Billing Class
Use this page to set up and edit billing classes. Billing classes provide flexibility when creating sales orders and invoices for billing schedules that use different billing cycles.
Calculate Projected Invoice Date
The following example demonstrates how the projected invoice date is calculated based on the different calculation options selected. A billing schedule has the following billing periods:
Billing period | Start date | End date |
Period 1 | February 05, 2021 | May 31, 2021 |
Period 2 | June 01, 2021 | August 31, 2021 |
Period 3 | September 01, 2021 | November 30, 2021 |
If the calculated projected invoice date is not a valid date, the projected invoice date is the last day of the calculated month.
From Billing Start Date
When Calculate from is Billing start date, the projected invoice dates for Period 1 with no other values specified is as follows. For descriptions of each calculation method, see the Fields section.
Calculation method | Projected invoice date |
None | February 05, 2021 |
Beginning of month | February 01, 2021 |
End of month | February 28, 2021 |
Beginning of period | February 05, 2021 |
Date | February 05, 2021 |
Continuing with calculating from Billing start date, the projected invoice dates for Period 1 with various values specified is as follows:
Calculation method | Prior months | Prior days | After months | After days | Days | Projected invoice date |
None | February 05, 2021 | |||||
Beginning of month | 1 | 1 | January 02, 2021 | |||
End of month | 1 | February 27, 2021 | ||||
Beginning of period | 1 | 3 | March 08, 2021 | |||
Date | 1 | 15 | March 15, 2021 |
From Billing End Date
When Calculate from is Billing end date, the projected invoice dates for Period 1 with no other values specified is as follows:
Calculation method | Projected invoice date |
None | May 31, 2021 |
Beginning of month | May 01, 2021 |
End of month | May 31, 2021 |
End of period | May 31, 2021 |
Date | May 31, 2021 |
Continuing with calculating from Billing end date, the projected invoice dates for Period 1 with various values specified is as follows:
Calculation method | Prior months | Prior days | After months | After days | Days | Projected invoice date |
None | May 31, 2021 | |||||
Beginning of month | 1 | 1 | April 02, 2021 | |||
End of month | 1 | May 30, 2021 | ||||
End of period | 1 | 3 | April 28, 2021 | |||
Date | 1 | 15 | June 15, 2021 |
Create a Billing Class
To create a billing class , follow these steps:
- Specify a unique Billing class name and Description.
- To have the invoice for the first billing period created immediately after the billing schedule is created and active, set Invoice first period immediately to Yes.
- In Calculate from, select whether to use the start or end date of a billing period from which to calculate the Projected invoice date.
- Select the Calculation method to use.
- If needed, specify the Prior days or Prior months and the After days or After months and the Days. The field boxes available depend on the calculation method selected. Different combinations of prior and after days and months can be used as follows.
- Prior days only
- Prior months only
- After days only
- After months only
- Prior days and After months
- Prior months and After days
- Select Save.
Billing classes that are used by billing schedules cannot be deleted.
Fields
The following field boxes are available:
Field | Description |
Billing class name | Specify a unique name for the billing class. |
Description | Specify a description for the billing class. |
Invoice first period immediately |
Indicates whether the invoice for the first billing period can be created immediately after billing schedule is created and active.
|
Projected invoice date | |
Calculate from |
Select whether to use the start or end date of a billing period from which to calculate the projected invoice date.
|
Calculation method |
Select the method by which to calculate the projected invoice date. When calculating the invoice creating date, the Calculate from value is considered. The prior and after days/months and the days option become available based on the calculation method selected. For examples, see Billing Class.
|
Prior days |
Specify the number (0 to 999) of days prior to set the projected invoice date. An empty value is considered zero (0). Only one of Prior days or After days can have a value. |
Prior months | Specify the number (0 to 999) of months prior to set the projected invoice date. An empty value is considered zero (0). Only one of Prior months or After months can have a value. |
After days | Specify the number (0 to 999) of days after to set the projected invoice date. An empty value is considered zero (0). Only one of Prior days or After days can have a value. |
After months | Specify the number (0 to 999) of months after to set the projected invoice date. An empty value is considered zero (0). Only one of Prior months or After months can have a value. |
Days |
Specify the day of the month (1 to 31) for the projected invoice date. |